Minutes for Meeting: 7:00 P.M., March 15, 2012
Members Present:  Ray Estes, Tim Collins, Peter Bradley, Samantha Anderson, and Sandra Cleary
School Resource Staff:   Dorothy Galo, John Ferris, and Roger Boddie
Professional Team:  Jim Jordan, Adam Bonosky, Kris Bradner, Cari Orsi, Kristy Lyons, and Mary Mahoney

R. Estes called meeting to order at 7:40 P.M.

Minutes for Building Committee meeting March 7, 2012 were approved as amended.

Design Update:

The Building Committee generally agreed with the plans and phasing/landscape designs as presented and with the progress update complete, C. Orsi and K. Bradner were excused from the meeting at 8:15pm.

R. Estes reported that the “Order of Conditions” issued by Hingham Conservation Commission for the project and delivered to the School Department on March 13, 2012. The Order includes 51 conditions for construction and post construction site use. The Planning Board has drafted its decision regarding site plan approval which should be issued in the near future. Board of Health has scheduled their project review hearing on March 21, 2012 at 7 PM. J. Jordan reported on efforts by Don Martinage, Martinage Engineering Associates, to confirm that the project filing and variance requests meet all of the Board’s needs and that Bruce Capman has indicated the filing is complete and ready for Board review on Wednesday.

Design Update is continued by J. Jordan:

R. Estes asked if exterior windows proposed for the Nurse’s Suite and SPED Suite are acceptable to the users. Committee discussion ensued regarding the proposed window type with agreement that the windows need to be operable.

M. Mahoney noted that at the last Building Committee meeting, the Committee discussed four (4) precast masonry panels proposed for the north exterior gym elevation and three quotes provided by the School Department for the panels. The quotes provided were based on the School Department’s mission statement and its three core beliefs: “Commitment to Learning”, “Fulfillment of Potential”, and “Service to Others”. R. Estes noted that the School Department’s mission statement has been revised to include five core beliefs. D. Galo provided a copy of the revised mission statement with five core beliefs.  Committee discussion ensued regarding the quotes with agreement to use the following four quotes: “Fulfillment of Individual Potential”, Respect for Self and Others”, Commitment to Life-long Learning”, “Civic Responsibility and Service to Others”.

M. Mahoney notes that if the design documents and cost estimates are acceptable to the Building Committee then the professional team needs approval and authorization by the Committee to submit the 100%  Construction Document Submittal to MSBA. S. Cleary moved to approve and authorize KBA to submit on behalf of the Building Committee the 100% Construction Document Submission to the Massachusetts School Building Authority (MSBA), seconded by S. Anderson. Unanimous vote to approve motion.

M. Mahoney reviewed the updated schedule which includes update on performance during the past month and refines dates for 100% Construction Document submission to MSBA, completion of contractor prequalification, issuance of bid documents and bid opening dates.

R. Estes noted that the schedule for future meetings includes April 4th and 25th and based on a scheduling conflict, the Committee was asked to move the April 4th meeting to April 3rd. Committee discussion ensued regarding schedule and need for meeting on April 3rd with agreement to revise the future meeting schedule to April 3rd and 25th.

With design progress update complete, J. Jordan and A. Bonosky were excused from the meeting at 10:31pm.

K. Lyons reported on progress by the Contractor Prequalification Subcommittee. Since the last Building Committee meeting, subcommittee members formalized and executed contractor evaluations, issued their final report to the Building Committee, and drafted the registry of prequalified firms and prequalification status letters. Notifications to firms and posting of the registry of prequalified firms will be completed by March 19th, so that firms not qualifying with have a period for appeal prior to issuance of bid documents. The registry of firms will need to be posted at the Awarding Authorities bid room and Commonwealth’s Comm-PASS system and it is recommended to post on the Awarding Authorities web page. KBA will coordinate the notification mailing, registry posting, response to public inquiry, response to appeals and will assemble records for the owner. Only those firms prequalified for the project will be invited to bid on the section of work for which they are prequalified. Building Committee discussion ensued regarding the draft list of prequalified firms, process for prequalification, and invitation to bid and expressed its gratitude to the Prequalification Committee members for all their efforts to advance the process for the project.

M. Mahoney updated progress with MSBA. The professional team drafted a joint response to MSBA 60% Construction Document review comments and today KBA forwarded the response to Jennifer Connarton at MSBA. Based on Building Committee vote this evening authorizing submission of the 100% Construction Documents, the professional team will complete its documentation for the submittal package and will submit to MSBA on or before April 6, 2012. Recently the School Department submitted an appeal on previous project invoices deemed ineligible for reimbursement. This appeal submission was taken by MSBA as submission of new invoices and reloaded to the Propay system putting the project over budget. MSBA contacted KBA regarding the overage and issues it was having understanding the bill breakdown for Ai3 invoices. MSBA was informed of the School Department intent to appeal ineligible invoices and KBA provided copies of all project invoice log reports to clarify Ai3 invoice billing. MSBA is reviewing the information and will advise. MSBA requested that the School Department include a copy of KBA’s invoice log with each future project reimbursement request. The School Department was informed of the filing request and will comply.

 M. Mahoney reported on (5) invoices presented for Committee consideration/approval as follows:

P. Bradley moved to approve invoices as reported, second by S. Cleary. Unanimous vote to approve all five invoices.
 
M. Mahoney reported that the budget will be updated to include the peer review performed by Seacoast Engineering Co., adding $9,900  to the committed column for “Geohydro, Wetland, reflagging” and includes the $990 LEED application fee in the committed column. Project invoices approved tonight are included in the expended to date column. Based on all project commitments and expenditures to date the project remains on budget.

Meeting adjourned at 11:00 P.M.