Greenbush Coordination Meeting Minutes
January 13, 2005

 

Status of Construction

Talbot's pump station continues.
48" work on Town Brook west of Hersey Street has begun.  Should be done next week.
Town Brook should be activated by the end of January.
Lincoln Street sewer is completed.  Road will be finished next week.
Work behind South Street pump station on transformers and emergency generator continues
Tide gate near harbor has been delivered.   However, due to fish concerns work will not begin until June.
Earth support work continues east of South Street, west of Central St. and between Central & Main.
Relocation of water line in Main Street will begin next week.
Mowing, brush cutting and tie rail removal has begun in West Hingham.

Verizon Update

Several meetings have taken place with Cashman to resolve relocation issue.
Town requests that overhead lines on South Street be moved underground.


Town's Concerns

Town would like to see overall project schedule now that permits are in hand.
Pipe splice use documentation and compaction reports have still not been provided by MBTA.
Some repairs are completed.  Camera inspection of additional sections is scheduled for next week.  Dave Polcari has requested a copy of the video tape.  Pressure testing of new force main is needed.  Sewer representative requested copy of as-built drawing of force main on Lincoln Street.
Dewatering bill still not paid.
Cashman will not be responsible for snow removal and sanding if road is not completed.
Paving on North Street needs to be temporary.  A letter has been sent to Cashman proposing an approach to temporary paving.
Signs that were removed during construction were identified and discussed.  Striping of crosswalks also needed.
Truck plan still needed for excavation material.