Status of Construction

Work on the Talbot's pump station continues.  Some sewer force main work remains to be done.
48" work on Town Brook west of Hersey Street continues.  Should be done next week.
Town Brook should be fully activated in February.
Work behind South Street pump station on transformers and emergency generator continues
Tide gate near harbor has been delivered.   However, due to fish concerns work will not begin until June.
Earth support work continues east of South Street, west of Central St. and between Central & Main.
Relocation of water line in Main Street will begin next week.
No right-of-way work for next 3 weeks.

Verizon Update

No Verizon representative in attendance
Meeting today to resolve issues with Cashman.
Town requests that overhead lines on South Street be moved underground.

Town's Concerns

Inspection of 60" sections of Town Brook needs to be scheduled.
The Town would like to walk the line with the arborist to inspect the marking of the area to be cleared.
Town would like to see overall project schedule now that permits are in hand.
Pipe splice has been inspected and approved.  Compaction reports have been reviewed and approved.
Some repairs are completed.  Camera inspection of additional sections is scheduled for next week.  Dave Polcari has requested a copy of the video tape.  Pressure testing done of new force main.  Sewer representative requested copy of as-built drawing and record drawing of force main that was installed on Lincoln Street.
Dewatering bill still not paid.  The December 9th  bills have also not been paid for work on South at Central.
Gaps in 48" pipe have been addressed.
Paving on North Street needs to be temporary.  A letter has been sent to Cashman proposing an approach to temporary paving.
Signs that were removed during construction were ordered.  Striping of crosswalks also needed.
Truck plan still needed for excavation material.
73 North Street requests repair of steps damaged during construction.
Structures in road need to be raised.
Complaint from neighbors regarding noise from pumps and generators on South Street
They request noise abatement measures.
A grate needed for the day-lighting structure installed for Town Brook.