Greenbush Coordination Meeting Notes
March 2, 2006

 


Greenbush Coordination Meeting Notes
March 2, 2006

Status of Construction

Fort Hill intersection continues.  A berm is needed on the right hand side.  A sign is needed at the island.  Hingham Light Plant has received approval for 2 new light poles.  Mass Electric pole needs to be removed.  The wires have been moved.
Excavation west of Central Street and west of South Street continues. 
Hull Street work began on February 28.  The contractor also wants to close Summer Street to begin work next week.
Fort Hill, South and West St. grade crossing may start in two weeks.
The contractor has delayed the closure of Weir Street.  The Town is looking to change the location of the cul-de-sac.  The Abbey is going to grant a license to permit the cul-de-sac partially on their property.
South Street is closed for excavation until April 14.
Work continues at West Hingham station platform over next few weeks.
A tide gate alternative was proposed for the Station Street parking lot. More data is needed.

Town's Concerns

Record drawing for force main and manuals are still outstanding.   Manhole cover is offset and needs to be realigned prior to final paving.  David Polcari of CDM presented a letter on excessive infiltration at North and Central Street.  There is a sag in the sewer pipe in North Street that needs to be addressed.  CBB has proposed a settlement to the Sewer Department.  CDM reviewed settlement and proposed an alternative amount.
The Town has approved the Town Brook siphon alternative.  The Town engineer approved a 36" design.   A letter requesting the alternative has been sent to the MBTA.
 The Town has provided estimate for North Street paving.  The Town requests an executed MOU from CBB.  There is still a disagreement on the Contractor's responsibilities.  Kevin McCrea will present estimate to upper management.  Mr. Doyle has tentatively approved the MOU.
Punch list continues.  Major items remaining are largely related to sewer work.  There is agreement by all parties on the outstanding issues.
Cliff Prentiss has produced a shop drawing for a gate design for the Town Brook to show DEP.  Drawing prepared and has been provided to CBB.  The Town has made a formal request to the MBTA.
The Town raised the concern about the amount of dewatering going on in the boat sections.  No change.
The Town raised a concern about waterproofing of the tunnel.
The Town Fire Department is looking to do some training in the tunnel.  Some training took place on February 2.  Group exercises have begun.


 

 

 


.