Status of Construction
Work on the Talbot's pump station, transformers and generators continues. Some sewer force main work remains to be done.
Manhole for Town Brook near Hersey Street completed.
The drain on Main Street continues. The by-pass of drainage has been moved to behind Sherwin Williams. Slurry wall panels will have to be built first.
Work behind South Street pump station on transformers and emergency generator continues.
Earth support work continues west of Central St. and between Central and Main St.
There is a new archeological dig between South and Main Streets. It could take a long time to resolve.
Catch basin at barbershop may be hooked up next week.
No right-of-way clearing work for next 3 weeks.
Verizon Update
Verizon has begun work on South Street on the modifications agreed to with Cashman.
Cables would be lifted around April 15.
Town requests that overhead lines on South Street be moved underground.
Town's Concerns
Inspection of Town Brook needs to be scheduled. A punch list will be developed by the Town and transmitted to Cashman.
The Town would like to walk the line with the arborist to inspect the marking of the area to be cleared.
Town would like to see overall project schedule now that permits are in hand.
Camera inspection of additional sewer sections is completed. Dave Polcari has requested a copy of the videotape. Sewer representative requested copy of as-built drawing and record drawing of force main that was installed on Lincoln Street.
Dewatering bill still not paid. The December 9th bills have also not been paid for work on South at Central.
Paving on North Street needs to be temporary. A letter has been sent to Cashman proposing an approach to temporary paving. The Town requests an answer next week.
Signs that were removed during construction were ordered. Striping of crosswalks also needed.
Truck plan still needed for excavation material. The estimate is for 15 trucks a day over a 3-month period, starting in May or June.
73 North Street requests repair of steps damaged during construction.
Finish grade at 79-87 North Street needs to be corrected.
Structures in road need to be raised.
A grate is needed for the day-lighting structure installed for Town Brook. This may be an environmental issue.