Downtown Tunnel Construction Update
March 16, 2006
South Street
Roof plank is being cast
Walls are being constructed
Working Saturdays to get job finished by mid-April
Blasting is going well
Central Street
Next street closure
Approximately closed at end of April
Will need 6 weeks
Will be left in binder course
Will work from west portal toward Central Street
Main Street
More involved - utilities and other drainage have to be addressed
Have to work around 4th of July holiday
All concrete work by August
Track to be laid in fall
.