Greenbush Downtown Tunnel Construction Update
March 16, 2006

 


Downtown Tunnel Construction Update
March 16, 2006


South Street

 Roof plank is being cast
 Walls are being constructed
 Working Saturdays to get job finished by mid-April
 Blasting is going well


Central Street

 Next street closure
 Approximately closed at end of April
 Will need 6 weeks
 Will be left in binder course
 Will work from west portal toward Central Street
 

Main Street

 More involved - utilities and other drainage have to be addressed
 Have to work around 4th of July holiday


All concrete work by August
Track to be laid in fall
 

 

 

 

 


.