Link back to Greenbush Minutes page
![]()
Status of Construction
Work on the Talbot's pump station, transformers and generators continues. Some sewer force main work remains to be done. Project will take 2 months to complete. Have to relocate electrical.
The drain on Main Street continues. The by-pass of drainage has been moved to behind Sherwin Williams. Slurry wall panels will have to be built first. Should be completed next week. The demolition of the 60" will take place next week. The 36" at the SSCC will take place next week and should be done the week of April 4.
Earth support work continues west of Central St. and between Central and Main St.
There is a new archeological dig between South and Main Streets. They have resumed work.
Catch basin at barbershop is hooked up but issues with elevation remain.
No right-of-way clearing work for next 3 weeks.
Verizon Update
Verizon has begun work on South Street on the modifications agreed to with Cashman.
Cables would be lifted around April 15. There will be a meeting on April 14 with Verizon to prepare for the cable lift.
Town requests that overhead lines on South Street be moved underground. The Town should contact Rick Colon.
Town's Concerns
Inspection of Town Brook needs to be scheduled. A punch list will be developed by the Town and transmitted to Cashman.
The Town would like to walk the line with the arborist to inspect the marking of the area to be cleared.
Town would like to see overall project schedule now that permits are in hand. It is under development.
Camera inspection of additional sewer sections is completed. Dave Polcari has requested a copy of the videotape. Sewer representative requested copy of as-built drawing of force main that was installed on Lincoln Street. Fiore has not made copies of videotape. The record drawing was delivered.
Dewatering bill has been paid. The pumping companies are being paid also.
Paving on North Street needs to be temporary. A letter has been sent to Cashman proposing an approach to temporary paving. Cashman is working on it.
Signs that were removed during construction were ordered and some have been replaced.. Striping of crosswalks also needed once the weather improves.
Truck plan still needed for excavation material. The estimate is for 15 trucks a day over a 3-month period, starting in May or June.
73 North Street requests repair of steps damaged during construction.
Finish grade at 79-87 North Street needs to be corrected, i.e. the curb needs to be reset.
Structures in road need to be raised.
A grate is needed for the day-lighting structure installed for Town Brook. This may be an environmental issue. Cliff Prentiss is working on it.
Parking: CBB has been complying. The Post Office is still a problem.