Greenbush Coordination Meeting Minutes
May 12, 2005

 

Status of Construction

Work on the Talbot's pump station, transformers and generators continues.  It should be done shortly.  May continue work on South Street immediately thereafter.
The 36" at the SSCC is finished.  The drain on South Street is next.
Excavation for the westerly boat section could begin as early as Friday but more likely on May 23rd.
Earth support work continues west of South St. two more weeks. Will continue east of South Street and between South and Main Streets.
The utility relocation in Central Street has begun and will end in the middle of June.  Central Street will be closed during this period.
Gas line work will start on May 10 on South Street.
Right-of-way clearing work and tie and rail removal continues.
The drainage punch list from the town has been sent. (Punch list activities have begun.)  Working on list.  Signs and line painting still needed.

Verizon - Meeting with Rick Colon on the Lifting of Existing Copper Cables by Cashman

Verizon knows who is served by the copper cables which are being moved.  Approximately 900 customers are involved.  A letter will be sent out to customers in the event of an outage.  The Selectmen should tell people to call Verizon in the event of a loss of service.  Last time customers did not call assuming Verizon knew that they lost service.
Deputy Chief Mark Duff will update the emergency contact list of town employees and provide it to Verizon.  Sue Sullivan will be contacted as a representative of downtown businesses.
The alternate fiber feed to Town Hall will be ready next week.  The Deputy Chief requests that 1212 and 2424 ring both in Dispatch and at Fire Headquarters.
Back up lines for the Fire Station have not been finished yet.

Town's Concerns

An agreement to do the skim coat paving in front of St. Paul's has been reached.  Pavement markings also need to be done.
Town would like to see overall project schedule now that permits are in hand.  (It is under development.)
Camera inspection of additional sewer sections is completed.  The video tape was delivered.  The Sewer Department has concerns about the inspection and the condition of the sewer. Sewer representative states that the as-built drawing of force main on Lincoln Street is lacking in detail.  Fiore and CBB are discussing.  Jim Dow presented a letter to Kevin McRea re:  sewer concerns.  Sewer representative asks for a notice before pump station begins operation.
Paving on North Street needs to be temporary.  A letter has been sent to Cashman proposing an approach to temporary paving.  (Waiting on DPW Bids) 
Signs that were removed during construction were ordered and some have been replaced. Striping of crosswalks and centerline on Station Street also needed once the weather improves.  The punch list work is ongoing.
Truck plan still needed for excavation material.  The estimate is for 15-30 trucks a day over a 3-month period, starting in May or June.  Town has developed  a plan and provided it to Cashman.
73 North Street requests repair of steps damaged during construction.  Tom Carroll is talking to homeowner.
A grate is needed for the day-lighting structure installed for Town Brook.  This may be an environmental issue.  Cliff Prentiss is working on it.  The Department of Marine Fisheries is opposed to grates.