Status of Construction
Work on the Talbot's pump station, transformers and generators continues. It should be done shortly. Work on South Street force main will start next week.
The drain on South Street has begun. Should be done by middle of next week.
Excavation for the westerly boat section began today.
Earth support work continues west of South St. two more weeks. Will continue east of South Street and between South and Main Streets.
The utility relocation in Central Street has begun and will end in the middle of June. Work is ahead of schedule. Central Street will be closed during this period.
Gas line work continues on South Street.
Right-of-way clearing work and tie and rail removal continues.
The drainage punch list from the town has been sent. (Punch list activities have begun.) Working on list. Signs and line painting still needed.
Verizon
Work is going well on raising cable.
The alternate fiber feed to Town Hall is ready. .
Back up lines for the Fire Station are at the station. Further work needs to be done at the station.
Town's Concerns
An agreement to do the skim coat paving in front of St. Paul's has been reached. Pavement markings also need to be done.
Town would like to see overall project schedule now that permits are in hand. (It is under development.)
Camera inspection of additional sewer sections is completed. The video tape was delivered. The Sewer Department has concerns about the inspection and the condition of the sewer. Sewer representative states that the as-built drawing of force main on Lincoln Street is lacking in detail. Fiore and CBB are discussing. Jim Dow presented a letter to Kevin McRea re: sewer concerns. Sewer representative asks for a notice before pump station begins operation.
Paving on North Street needs to be temporary. A letter has been sent to Cashman proposing an approach to temporary paving. (Waiting on DPW Bids)
Signs that were removed during construction were ordered and some have been replaced. Striping of crosswalks and centerline on Station Street also needed once the weather improves. The punch list work is ongoing.
Truck plan still needed for excavation material. The estimate is for 15-30 trucks a day over a 3-month period, starting in May or June. Town has developed a plan and provided it to Cashman.
73 North Street requests repair of steps damaged during construction. Tom Carroll is talking to homeowner.
A grate is needed for the day-lighting structure installed for Town Brook. This may be an environmental issue. Cliff Prentiss is working on it. The Department of Marine Fisheries is opposed to grates.
The sprinkler stand pipes for the tunnel need to be reviewed again.