Status of Consruction
Work on Talbot's pump station, transformers and generators should be done shortly.
Work on South Street force main will start this week.
The drain on South Street has begun. They are not digging the tunnel! The catch basin is off line. They are looking into this.
Excavation of westerly boat section begun last week.
Earth support work continues west of South Street., June 13. Gas line relocation.
Utility relocation Central street will end middle of June.
Gas line work cont. on South Street. June 6 Earth support.Clearing of right of way work cont.
drainage punch list has been sent. Working on it.
Verizon
Cable has been raised.
Alternate fiber cable feed to Town Hall is ready.
Back up lines for Fire Station. Time delay on hook up if emergency. 2424/1212 lines will be set
5/26. lines are in basement.
Verizon has concerns about cables being exposed by hole caving due to rain. Discussed.
Town's Concerns
Pavement markings are weather dependant.
Overall project schedule?
North Street, Main to Central not videoed. Discussing it. Fiore had not responded to letters.
Paving North Street?
Signs removed or missing during construction?
Truck plan for excavated material needed. Town has given plan to Cashman.
73 North Street repair of steps. No progress reported.
A Grate for day-lighting structure for Town Brook. Hinge gate discussed. Cliff working on it.
Sprinkler stand pipe need to be reviewed.