Status of Construction
Earth support work on both South Street and Central Street continues.
Central Street pothole work is complete.
Fort Hill crossing and intersection work continues.
The contractor requests to close Weir Street. The Town agrees as long as the residents are notified in advance.
The west boat section work has encountered a great deal of water. Excavation work continues.
Clearing right-of-way and tie and rail removal continues.
Town's Concerns
Record drawing for force main and resolution of TV inspection at Talbots and sewer repair on North Street still outstanding. Manhole cover is offset and needs to be realigned prior to final paving. David Polcari of CDM presented a letter on excessive infiltration at North and Central Street. The potential charge to the contractor is $250,000.
The Town is still exploring the Town Brook easement.
The Town engineer suggests a 42" or 48" siphon for Town Brook.
The Town has provided estimate for North Street paving. The Town requests an executed MOU from CBB.
Punch list continues.
Cliff Prentiss will produce a shop drawing for a gate design for the Town Brook to show DEP.