Status of Construction
Earth support work on both South Street and Central Street continues.
Fort Hill crossing and intersection work continues.
The contractor has delayed the closure of Weir Street. The Town is looking to change the location of the cul-de-sac.
The west boat section work has encountered a great deal of water. Excavation work continues. Excavation of the existing boat section will begin next week.
Clearing right-of-way and tie and rail removal continues.
Town's Concerns
Record drawing for force main and resolution of TV inspection at Talbots and sewer repair on North Street still outstanding. Manhole cover is offset and needs to be realigned prior to final paving. David Polcari of CDM presented a letter on excessive infiltration at North and Central Street.
The Town is still exploring the Town Brook easement. The Town engineer suggests a 42" or 48" siphon for Town Brook.
The Town has provided estimate for North Street paving. The Town requests an executed MOU from CBB.
Punch list continues.
Cliff Prentiss will produce a shop drawing for a gate design for the Town Brook to show DEP.
The Town raised the concern about the amount of dewatering going on in the boat sections.