Status of Construction

Clean-up North Street sidewalk continues.
Water line relocation at Hersey Street will be finished next week.
54" work would begin again next week
72" work at Station and North Streets will begin Monday.
Work should take 3 weeks.
Sewer replacement complete in Central Street.  Sewer work will continue up North Street a week
from Monday.
Gas work will be done early next week at Station Street

Verizon

Discussions are ongoing.

Aquarion

No report

Town's Concern

Sidewalk work needs to be completed.