Status of Construction
Clean-up North Street sidewalk continues.
Water line relocation at Hersey Street will be finished next week.
54" work would begin again next week
72" work at Station and North Streets will begin Monday.
Work should take 3 weeks.
Sewer replacement complete in Central Street. Sewer work will continue up North Street a week
from Monday.
Gas work will be done early next week at Station Street
Verizon
Discussions are ongoing.
Aquarion
No report
Town's Concern
Sidewalk work needs to be completed.