Greenbush Coordination Meeting Minute
October 7, 2004

 

Status of Construction

North Street sidewalk should be done next week.
Hersey Street water work should be done.
54" work will not begin for a couple of weeks.
North and Station Streets should be done in 3 weeks.
72" drain and sewer installation should take at least 3 weeks.
Archeological permit needed for sewer work on North Street.

Verizon

Need to get into St. Paul's manhole this weekend.

Aquarion

No report.

Town's Concerns

Pipe splice use documentation and compaction reports have still not been provided.
Tape of sewer inspection needs to be provided to the Sewer Commission.
Dewatering  bill still needs to be paid.
Signs on trench heading up North St. need to be removed.