Status of Construction
North Street sidewalk should be done next week.
Hersey Street water work should be done.
54" work will not begin for a couple of weeks.
North and Station Streets should be done in 3 weeks.
72" drain and sewer installation should take at least 3 weeks.
Archeological permit needed for sewer work on North Street.
Verizon
Need to get into St. Paul's manhole this weekend.
Aquarion
No report.
Town's Concerns
Pipe splice use documentation and compaction reports have still not been provided.
Tape of sewer inspection needs to be provided to the Sewer Commission.
Dewatering bill still needs to be paid.
Signs on trench heading up North St. need to be removed.