Greenbush Coordination Meeting Minutes
October 14, 2004

 

Status of Construction

Waiting for crew to do the North Street sidewalk.
54" work will not begin for a couple of weeks.
North and Station Streets should be done in 2 weeks.
72" drain between Main and Central will take 2-3 more weeks.
Gas line on Station Street on holdup, should be done shortly.
Talbot's pump station to start November 1.  One month construction time.
Lincoln Street sewer to start October 25 and take 3 weeks.

Verizon

Need to get into St. Paul's manhole again this weekend.

Town's Concerns

Pipe splice use documentation and compaction reports have still not been provided by MBTA.
Sewer inspection has been done but the tape of the inspection is missing.
Dewatering bill still not paid.
Who will be responsible for snow removal and sanding.
Is the work area to be expanded in December?