Status of Construction
Archeological work is done for now.
Talbot's pump station continues. the construction will take at least several weeks.
72" drain at Central St. will start the week of December 20 in the existing trench.
54" work is done at the moment until permits come in.
The North Street sidewalk will be finished next week.
Lincoln Street sewer to start after Christmas.
Work behind South Street pump station on transformers and emergency generator continues.
Work around tide gate near harbor will take place over next several weeks.
Earth support work will shut down during Christmas week.
Verizon Update
The Board of Selectmen will discuss alteration of the grant of location on December 14, 2004 at 6:30 PM.
Zoning Board of Appeals hearing next Thursday on the new equipment box on Central Street.
Town's Concerns
Pipe splice use documentation and compaction reports have still not been provided by MBTA.
Sewer inspection has been done. Some repairs are needed. Camera inspection of additional sections is still needed.
Dewatering bill still not paid.
Cashman will be responsible for snow removal and sanding if road is not completed.
Paving on North Street needs to be temporary. A letter has been sent to Cashman proposing an approach to temporary paving.
Blue plastic sheeting was removed.
Truck plan still needed for excavation material.